PMI PMP – Project Scope Management body of knowledge

Set -1 : 30 question
What is the primary goal of Project Scope Management?
a) To define and control what is included and excluded in the project
b) To create a project schedule
c) To allocate resources effectively
d) To manage stakeholder expectations
Answer: a) To define and control what is included and excluded in the project
Which document provides a detailed description of the project scope?
a) Scope Management Plan
b) Project Charter
c) Requirements Traceability Matrix
d) Project Scope Statement
Answer: d) Project Scope Statement
What is the purpose of the Work Breakdown Structure (WBS)?
a) To list project risks
b) To break down the project scope into manageable components
c) To allocate resources
d) To define quality standards
Answer: b) To break down the project scope into manageable components
What is scope creep?
a) Reduction in project scope due to budget constraints
b) Uncontrolled expansion of project scope without approval
c) Introduction of new team members
d) A change in the project schedule
Answer: b) Uncontrolled expansion of project scope without approval
What is the key input for defining scope?
a) Work Breakdown Structure
b) Requirements documentation
c) Quality Management Plan
d) Change Control Log
Answer: b) Requirements documentation
Which tool or technique is used to validate scope?
a) Inspection
b) Benchmarking
c) Monte Carlo Simulation
d) Root Cause Analysis
Answer: a) Inspection
What is included in the Scope Baseline?
a) Project Schedule and Budget
b) Project Scope Statement, WBS, and WBS Dictionary
c) Risk Management Plan
d) Stakeholder Register
Answer: b) Project Scope Statement, WBS, and WBS Dictionary
Who is responsible for approving project scope changes?
a) Project Manager
b) Change Control Board
c) Project Sponsor
d) Team Members
Answer: b) Change Control Board
What does the term “scope validation” refer to?
a) Controlling scope changes
b) Ensuring the project scope aligns with stakeholder expectations
c) Formally accepting completed deliverables
d) Documenting project risks
Answer: c) Formally accepting completed deliverables
Which document ensures that all project requirements are addressed?
a) Requirements Traceability Matrix
b) Scope Management Plan
c) Change Log
d) Risk Register
Answer: a) Requirements Traceability Matrix
Which of the following is a technique for collecting requirements?
a) Root Cause Analysis
b) Interviews
c) Monte Carlo Simulation
d) Control Charts
Answer: b) Interviews
What is the WBS Dictionary used for?
a) Defining work packages and providing detailed information about each
b) Mapping project risks
c) Scheduling project activities
d) Estimating project costs
Answer: a) Defining work packages and providing detailed information about each
When is a deliverable considered complete during scope validation?
a) When it meets predefined acceptance criteria
b) When it is delivered on time
c) When the project sponsor reviews it
d) When it is aligned with the budget
Answer: a) When it meets predefined acceptance criteria
What is the main output of the process “Control Scope”?
a) Change Requests
b) Lessons Learned Register
c) Project Charter
d) Accepted Deliverables
Answer: a) Change Requests
Which process ensures that all approved changes are reflected in the project scope?
a) Validate Scope
b) Control Scope
c) Define Scope
d) Develop Project Charter
Answer: b) Control Scope
What is the primary benefit of the Collect Requirements process?
a) Establishing communication protocols
b) Defining and managing stakeholder expectations
c) Aligning project activities with organizational strategy
d) Estimating project costs
Answer: b) Defining and managing stakeholder expectations
Which of the following is not part of the scope definition process?
a) Analyzing risks
b) Developing the project scope statement
c) Creating a Work Breakdown Structure (WBS)
d) Identifying deliverables
Answer: a) Analyzing risks
What does the term “gold plating” refer to in project management?
a) Delivering more than the scope requires without approval
b) Achieving all project milestones ahead of schedule
c) Enhancing deliverables after stakeholder review
d) Reducing project costs to meet budget constraints
Answer: a) Delivering more than the scope requires without approval
What is the main purpose of scope control?
a) Tracking project progress
b) Monitoring project budgets
c) Preventing scope creep
d) Scheduling project activities
Answer: c) Preventing scope creep
What is the first step in the Define Scope process?
a) Create WBS
b) Analyze project deliverables
c) Review requirements documentation
d) Develop the Scope Management Plan
Answer: c) Review requirements documentation
Which tool is most useful in understanding stakeholder needs for project scope?
a) Focus Groups
b) Pareto Analysis
c) Gantt Chart
d) Risk Breakdown Structure
Answer: a) Focus Groups
What is the main purpose of the Create WBS process?
a) Estimating project costs
b) Breaking project deliverables into smaller, manageable components
c) Allocating resources
d) Establishing communication protocols
Answer: b) Breaking project deliverables into smaller, manageable components
What ensures traceability of requirements throughout the project lifecycle?
a) Scope Management Plan
b) Requirements Traceability Matrix
c) Project Charter
d) Risk Register
Answer: b) Requirements Traceability Matrix
Which technique is used to prioritize requirements during scope management?
a) MoSCoW Analysis
b) Earned Value Management
c) Critical Path Method
d) Monte Carlo Simulation
Answer: a) MoSCoW Analysis
What is the primary output of the Define Scope process?
a) Scope Management Plan
b) Project Scope Statement
c) Work Breakdown Structure
d) Requirements Documentation
Answer: b) Project Scope Statement
Who is typically responsible for scope validation?
a) Project Sponsor
b) Project Manager
c) Key Stakeholders
d) Change Control Board
Answer: c) Key Stakeholders
What is included in a Scope Management Plan?
a) Risk mitigation strategies
b) How project scope will be defined, validated, and controlled
c) Communication protocols for the project team
d) Budget allocation methods
Answer: b) How project scope will be defined, validated, and controlled
Which process involves reviewing work products to ensure deliverables meet requirements?
a) Validate Scope
b) Control Scope
c) Collect Requirements
d) Develop Project Charter
Answer: a) Validate Scope
What is the relationship between project scope and product scope?
a) They are the same
b) Project scope is broader than product scope
c) Product scope is a subset of project scope
d) They are unrelated
Answer: c) Product scope is a subset of project scope
Which of the following is a critical element in controlling scope?
a) Stakeholder communication
b) Regular project audits
c) Change control processes
d) Resource leveling
Answer: c) Change control processes
Set -2 : 30 question ——————————
What is the primary focus of the Collect Requirements process?
a) Developing a comprehensive schedule
b) Identifying and documenting stakeholder needs and expectations
c) Allocating resources effectively
d) Controlling project costs
Answer: b) Identifying and documenting stakeholder needs and expectations
Which technique is commonly used during the Define Scope process to clarify deliverables?
a) SWOT Analysis
b) Prototyping
c) Risk Breakdown Structure
d) Monte Carlo Simulation
Answer: b) Prototyping
What is a key output of the Create WBS process?
a) Scope Baseline
b) Requirements Documentation
c) Activity List
d) Cost Baseline
Answer: a) Scope Baseline
Which document helps ensure all project deliverables are included in the project scope?
a) Project Charter
b) Project Scope Statement
c) Stakeholder Register
d) Issue Log
Answer: b) Project Scope Statement
What is the primary purpose of the Validate Scope process?
a) Identifying scope changes
b) Ensuring that deliverables meet the acceptance criteria
c) Monitoring overall project performance
d) Revising the Scope Management Plan
Answer: b) Ensuring that deliverables meet the acceptance criteria
What is a common cause of scope creep?
a) Poor stakeholder communication
b) Inadequate change control processes
c) Over-allocated resources
d) Insufficient project funding
Answer: b) Inadequate change control processes
What is included in a Work Breakdown Structure (WBS)?
a) A detailed project budget
b) A hierarchical breakdown of project deliverables
c) A list of project risks
d) A summary of resource allocation
Answer: b) A hierarchical breakdown of project deliverables
Which of the following helps manage scope-related conflicts during a project?
a) Stakeholder Engagement Plan
b) Change Control Board
c) Resource Management Plan
d) Risk Mitigation Plan
Answer: b) Change Control Board
What is a key benefit of defining the project scope early?
a) Reduces the likelihood of cost overruns
b) Eliminates the need for risk management
c) Increases stakeholder dissatisfaction
d) Prevents team communication
Answer: a) Reduces the likelihood of cost overruns
What is the main goal of scope management?
a) To deliver projects within budget
b) To ensure the project includes all required work and nothing extra
c) To minimize project duration
d) To allocate resources efficiently
Answer: b) To ensure the project includes all required work and nothing extra
What document is updated when a scope change is approved?
a) Risk Register
b) Project Schedule
c) Scope Baseline
d) Stakeholder Register
Answer: c) Scope Baseline
What tool is most useful for breaking down complex deliverables into smaller components?
a) Responsibility Assignment Matrix
b) Work Breakdown Structure (WBS)
c) Critical Path Method
d) Histogram
Answer: b) Work Breakdown Structure (WBS)
What does the term “gold plating” refer to in scope management?
a) Including additional features beyond scope requirements
b) Implementing unnecessary quality controls
c) Allocating extra resources to critical tasks
d) Delivering all work within the baseline scope
Answer: a) Including additional features beyond scope requirements
Which tool or technique is used to gather requirements from a large audience?
a) Surveys
b) Brainstorming
c) Focus Groups
d) Interviews
Answer: a) Surveys
What is a scope baseline composed of?
a) Project Charter, Requirements Documentation, and Activity List
b) Project Scope Statement, WBS, and WBS Dictionary
c) Risk Register, Cost Baseline, and Schedule Baseline
d) Stakeholder Register, Communication Plan, and Risk Matrix
Answer: b) Project Scope Statement, WBS, and WBS Dictionary
What is the role of a requirements traceability matrix in scope management?
a) To track project costs
b) To link requirements to project deliverables
c) To outline the change control process
d) To prioritize project risks
Answer: b) To link requirements to project deliverables
Which technique is commonly used to identify scope risks?
a) Delphi Technique
b) SWOT Analysis
c) Risk Assessment Matrix
d) Monte Carlo Simulation
Answer: b) SWOT Analysis
What is the result of poor scope definition?
a) Improved team morale
b) Scope creep and budget overruns
c) Enhanced stakeholder communication
d) Reduced project duration
Answer: b) Scope creep and budget overruns
What is a WBS dictionary?
a) A glossary of project management terms
b) Detailed information about each WBS element
c) A record of stakeholder contact details
d) A listing of project resources and their costs
Answer: b) Detailed information about each WBS element
Who typically approves the project scope statement?
a) Project Team
b) Project Sponsor
c) Change Control Board
d) Project Manager
Answer: b) Project Sponsor
Which document describes how changes to project scope will be managed?
a) Communication Plan
b) Scope Management Plan
c) Risk Management Plan
d) Quality Management Plan
Answer: b) Scope Management Plan
What is the difference between product scope and project scope?
a) Product scope refers to the features of the product; project scope includes all work required to deliver
the product
b) Project scope is broader than product scope
c) Product scope includes risk management; project scope does not
d) They are essentially the same
Answer: a) Product scope refers to the features of the product; project scope includes all work required
to deliver the product
What is a primary function of the Control Scope process?
a) Ensuring that project activities are on schedule
b) Monitoring the status of project scope and managing scope changes
c) Adjusting resources to meet schedule requirements
d) Communicating updates to stakeholders
Answer: b) Monitoring the status of project scope and managing scope changes
What tool is often used to visually show the hierarchy of project deliverables?
a) WBS
b) Gantt Chart
c) PERT Chart
d) Ishikawa Diagram
Answer: a) WBS
Which stakeholder has the authority to accept project deliverables?
a) Project Manager
b) Project Sponsor
c) Key Stakeholders
d) Quality Assurance Team
Answer: c) Key Stakeholders
What is the result of not involving stakeholders in scope management?
a) Improved project timelines
b) Increased likelihood of scope-related conflicts
c) Greater adherence to project requirements
d) Enhanced team communication
Answer: b) Increased likelihood of scope-related conflicts
Which process ensures that all necessary work is included in the project?
a) Plan Scope Management
b) Validate Scope
c) Define Scope
d) Create WBS
Answer: c) Define Scope
What is the primary purpose of a Change Control Board in scope management?
a) Approving and monitoring scope changes
b) Prioritizing project risks
c) Evaluating team performance
d) Reviewing financial performance
Answer: a) Approving and monitoring scope changes
Which type of analysis is used to ensure scope alignment with project objectives?
a) Document Analysis
b) Variance Analysis
c) Risk Analysis
d) Trend Analysis
Answer: a) Document Analysis
What is an important characteristic of a well-defined scope?
a) Flexibility to add features without approval
b) Specific, measurable, and achievable objectives
c) High-level descriptions with minimal detail
d) Exclusion of stakeholder input
Answer: b) Specific, measurable, and achievable objectives
Set -3 : 40 question —————————-
Which document is critical for managing stakeholder expectations about project scope?
a) Risk Register
b) Project Scope Statement
c) Issue Log
d) Communication Plan
Answer: b) Project Scope Statement
What process ensures that scope changes are properly managed?
a) Perform Integrated Change Control
b) Validate Scope
c) Define Scope
d) Develop Project Charter
Answer: a) Perform Integrated Change Control
Which activity is typically part of the Collect Requirements process?
a) SWOT Analysis
b) Interviews with stakeholders
c) Root Cause Analysis
d) Risk Categorization
Answer: b) Interviews with stakeholders
What is a decomposition technique used in scope management?
a) Creating Work Packages in a WBS
b) Preparing a Probability and Impact Matrix
c) Conducting Cost-Benefit Analysis
d) Performing Monte Carlo Simulation
Answer: a) Creating Work Packages in a WBS
What is the primary purpose of the Define Scope process?
a) To prepare the Project Schedule
b) To establish detailed boundaries of the project
c) To assign team roles and responsibilities
d) To create the Resource Management Plan
Answer: b) To establish detailed boundaries of the project
What is an essential element of a Work Breakdown Structure (WBS)?
a) Budget Allocation
b) Deliverable-Oriented Hierarchy
c) Detailed Schedule
d) Resource Assignments
Answer: b) Deliverable-Oriented Hierarchy
Which tool is helpful for prioritizing requirements during the Collect Requirements process?
a) MoSCoW Analysis
b) Fishbone Diagram
c) Control Charts
d) Ishikawa Diagram
Answer: a) MoSCoW Analysis
What does “scope creep” refer to in project management?
a) Unapproved additions to project scope
b) Delay in project timelines
c) Unexpected resource constraints
d) Decline in stakeholder satisfaction
Answer: a) Unapproved additions to project scope
Which type of requirements relate to system performance or user interface?
a) Functional Requirements
b) Non-functional Requirements
c) Regulatory Requirements
d) Project Constraints
Answer: b) Non-functional Requirements
What is the focus of the Validate Scope process?
a) Ensuring stakeholder approval of deliverables
b) Re-estimating project costs
c) Refining the Scope Baseline
d) Managing resource allocation
Answer: a) Ensuring stakeholder approval of deliverables
What technique involves visually representing ideas for requirements gathering?
a) Mind Mapping
b) Pareto Analysis
c) Critical Path Method
d) Earned Value Analysis
Answer: a) Mind Mapping
What is the primary goal of the Create WBS process?
a) To identify project risks
b) To define and organize project deliverables
c) To monitor project scope
d) To allocate resources
Answer: b) To define and organize project deliverables
What document outlines how scope will be defined, validated, and controlled?
a) Project Charter
b) Scope Management Plan
c) Stakeholder Engagement Plan
d) Quality Management Plan
Answer: b) Scope Management Plan
Which stakeholder is typically responsible for accepting project deliverables?
a) Project Team
b) Project Sponsor
c) Quality Assurance Manager
d) Procurement Manager
Answer: b) Project Sponsor
What does the term “requirements traceability” mean in scope management?
a) Tracking the origin and fulfillment of requirements
b) Identifying project risks
c) Validating changes in project scope
d) Linking schedule milestones to deliverables
Answer: a) Tracking the origin and fulfillment of requirements
What is an example of a project assumption that might be documented during scope planning?
a) Team members will have the necessary skills
b) Inflation rates will increase by 5%
c) A specific technology will become obsolete
d) Legal compliance will be waived
Answer: a) Team members will have the necessary skills
What tool can help resolve conflicting requirements?
a) Facilitation Workshops
b) Cost-Benefit Analysis
c) Variance Analysis
d) Fishbone Diagram
Answer: a) Facilitation Workshops
What process is typically responsible for revising the WBS?
a) Define Scope
b) Control Scope
c) Validate Scope
d) Collect Requirements
Answer: b) Control Scope
Which deliverables are most often excluded from the project scope?
a) Non-essential deliverables not critical to project success
b) All risk mitigation strategies
c) Deliverables required by regulatory compliance
d) Approved additional features requested by key stakeholders
Answer: a) Non-essential deliverables not critical to project success
What document defines the high-level boundaries of the project?
a) Project Scope Statement
b) Project Charter
c) WBS Dictionary
d) Stakeholder Engagement Plan
Answer: b) Project Charter
What is the purpose of a Scope Change Control System?
a) To approve minor project cost adjustments
b) To manage changes to the project scope systematically
c) To monitor stakeholder communications
d) To revise resource allocation strategies
Answer: b) To manage changes to the project scope systematically
What is the primary role of the project manager in scope management?
a) Approve changes to the project budget
b) Ensure all work aligns with the agreed-upon scope
c) Finalize quality control measures
d) Oversee stakeholder procurement
Answer: b) Ensure all work aligns with the agreed-upon scope
What does a WBS Dictionary typically include?
a) Roles and responsibilities for each team member
b) Detailed descriptions of WBS components
c) Cost estimates for deliverables
d) Milestones and performance metrics
Answer: b) Detailed descriptions of WBS components
What process ensures deliverables meet the stated acceptance criteria?
a) Validate Scope
b) Monitor and Control Project Work
c) Plan Scope Management
d) Develop Project Charter
Answer: a) Validate Scope
What term describes work performed beyond the agreed-upon scope?
a) Scope Creep
b) Schedule Compression
c) Risk Mitigation
d) Overlap Work
Answer: a) Scope Creep
What is a key element of the Define Scope process?
a) Development of a detailed Risk Register
b) Creation of the Project Scope Statement
c) Prioritization of project risks
d) Formulation of a resource calendar
Answer: b) Creation of the Project Scope Statement
What is a fundamental goal of project scope management?
a) Deliver projects ahead of schedule
b) Ensure all required work is included and unnecessary work is excluded
c) Increase the complexity of project deliverables
d) Maximize project costs to expand scope
Answer: b) Ensure all required work is included and unnecessary work is excluded
Which process defines how requirements will be documented and managed?
a) Collect Requirements
b) Plan Scope Management
c) Control Scope
d) Validate Scope
Answer: b) Plan Scope Management
What type of information is captured in the Project Scope Statement?
a) Budget and cost estimates
b) Detailed project requirements, exclusions, and constraints
c) Risk mitigation strategies
d) Communication matrix details
Answer: b) Detailed project requirements, exclusions, and constraints
Which technique can help ensure stakeholder involvement in scope planning?
a) Stakeholder Workshops
b) Resource Allocation Charts
c) Cost-Benefit Analysis
d) Statistical Sampling
Answer: a) Stakeholder Workshops
What is the primary purpose of the Scope Baseline?
a) To track project progress against cost estimates
b) To serve as a reference for managing and controlling project scope
c) To define the roles and responsibilities of the project team
d) To establish communication protocols for stakeholders
Answer: b) To serve as a reference for managing and controlling project scope
Which document helps in identifying scope exclusions?
a) Project Charter
b) Project Scope Statement
c) Requirements Management Plan
d) Stakeholder Register
Answer: b) Project Scope Statement
What is the purpose of conducting product analysis during scope definition?
a) To evaluate the product’s quality control measures
b) To determine project deliverables and their features
c) To assess stakeholder feedback
d) To validate scope with project sponsors
Answer: b) To determine project deliverables and their features
What does the Control Scope process primarily focus on?
a) Minimizing changes to the project schedule
b) Managing scope changes and ensuring they are within the baseline
c) Prioritizing project risks and constraints
d) Monitoring stakeholder engagement levels
Answer: b) Managing scope changes and ensuring they are within the baseline
What tool is commonly used for visually breaking down project deliverables?
a) Work Breakdown Structure (WBS)
b) Gantt Chart
c) Ishikawa Diagram
d) Pareto Chart
Answer: a) Work Breakdown Structure (WBS)
What is the main output of the Collect Requirements process?
a) Requirements Traceability Matrix
b) Risk Management Plan
c) Stakeholder Engagement Plan
d) Communication Matrix
Answer: a) Requirements Traceability Matrix
Which stakeholder group is typically most involved in defining project requirements?
a) End users
b) Procurement team
c) Quality assurance team
d) Risk management team
Answer: a) End users
What does the WBS Dictionary ensure?
a) Proper communication between stakeholders
b) Clarification and detailed descriptions of WBS elements
c) Efficient resource allocation for team members
d) Minimization of project risks
Answer: b) Clarification and detailed descriptions of WBS elements
Which technique is used to validate that all project requirements are fulfilled?
a) Requirements Traceability
b) Quality Audits
c) Performance Reporting
d) Statistical Sampling
Answer: a) Requirements Traceability
What is a primary challenge in managing project scope?
a) Securing adequate funding for project resources
b) Balancing stakeholder expectations with project constraints
c) Identifying all potential risks in the project lifecycle
d) Allocating time for training project team members
Answer: b) Balancing stakeholder expectations with project constraints

×