PMI PMP Certification Practice Test – 100 Questions for Exam Preparation – Set 1

  1. What is the primary purpose of a project charter?
    a) To define the detailed project schedule
    b) To authorize the project and give the project manager authority
    c) To approve the final deliverable
    d) To assign all project team members
    Answer: b) To authorize the project and give the project manager authority
  2. What is the main output of the Develop Project Charter process?
    a) Project Scope Statement
    b) Business Case
    c) Project Charter
    d) Project Management Plan
    Answer: c) Project Charter
  3. A project manager is assigned after the project charter is approved. What should the project manager do first?
    a) Create the work breakdown structure
    b) Review the charter and understand project objectives
    c) Start executing the project work
    d) Close procurement contracts
    Answer: b) Review the charter and understand project objectives
  4. Which document explains why the project is being undertaken from a business perspective?
    a) Business Case
    b) Risk Register
    c) Stakeholder Register
    d) Issue Log
    Answer: a) Business Case
  5. What is the best definition of project success in modern project management?
    a) Completing all tasks exactly as planned
    b) Delivering outputs only
    c) Delivering value and achieving intended outcomes
    d) Avoiding all risks
    Answer: c) Delivering value and achieving intended outcomes
  6. A project sponsor asks why a project should continue after major market changes. What should the project manager review first?
    a) Team charter
    b) Business case and benefits plan
    c) Procurement documents
    d) Resource calendar
    Answer: b) Business case and benefits plan
  7. What is the main purpose of project governance?
    a) To remove all project risks
    b) To provide decision-making, oversight and accountability
    c) To replace the project manager
    d) To approve only technical deliverables
    Answer: b) To provide decision-making, oversight and accountability
  8. Which project document identifies people, groups or organizations affected by the project?
    a) Risk Register
    b) Stakeholder Register
    c) Cost Baseline
    d) Quality Report
    Answer: b) Stakeholder Register
  9. A stakeholder has high power and high interest in the project. What is the best engagement strategy?
    a) Monitor only
    b) Keep satisfied with limited updates
    c) Manage closely
    d) Ignore unless issues occur
    Answer: c) Manage closely
  10. What is the purpose of stakeholder analysis?
    a) To replace communication planning
    b) To identify stakeholder needs, influence and expectations
    c) To assign project tasks
    d) To calculate project cost
    Answer: b) To identify stakeholder needs, influence and expectations
  11. A key stakeholder strongly disagrees with the project direction. What should the project manager do first?
    a) Escalate immediately to the sponsor
    b) Remove the stakeholder from communications
    c) Understand the concern and analyze its impact
    d) Change the project scope immediately
    Answer: c) Understand the concern and analyze its impact
  12. Which document defines how project information will be shared?
    a) Communications Management Plan
    b) Risk Management Plan
    c) Scope Baseline
    d) Procurement Statement of Work
    Answer: a) Communications Management Plan
  13. A stakeholder says they are receiving too much technical detail. What should the project manager do?
    a) Stop sending updates
    b) Tailor communication to stakeholder needs
    c) Send the same report more often
    d) Ask the team to communicate directly only
    Answer: b) Tailor communication to stakeholder needs
  14. What is the main purpose of a team charter?
    a) To authorize the project
    b) To define team values, working agreements and expectations
    c) To replace the project schedule
    d) To approve vendor contracts
    Answer: b) To define team values, working agreements and expectations
  15. A team is newly formed and members are unclear about roles. What should the project manager do?
    a) Let the team resolve it later
    b) Clarify roles, responsibilities and decision rights
    c) Escalate to the customer
    d) Reduce the project scope
    Answer: b) Clarify roles, responsibilities and decision rights
  16. Which leadership style is most useful when the team is skilled and motivated?
    a) Command-and-control
    b) Servant leadership
    c) Autocratic leadership
    d) Passive leadership
    Answer: b) Servant leadership
  17. In an agile project, what is the project manager’s most appropriate role?
    a) Assign every task daily
    b) Remove impediments and support team collaboration
    c) Approve every line of code
    d) Prevent stakeholder feedback
    Answer: b) Remove impediments and support team collaboration
  18. A conflict arises between two team members. What should the project manager do first?
    a) Ignore the conflict
    b) Encourage direct and respectful discussion
    c) Remove both team members
    d) Change the project deadline
    Answer: b) Encourage direct and respectful discussion
  19. Which conflict resolution approach usually produces the most lasting solution?
    a) Avoiding
    b) Forcing
    c) Collaborating
    d) Smoothing
    Answer: c) Collaborating
  20. A team member lacks the skill needed for an assigned task. What is the best response?
    a) Blame the team member
    b) Provide coaching, training or support
    c) Remove the task from the project
    d) Ignore the issue until testing
    Answer: b) Provide coaching, training or support
  21. What is psychological safety in a project team?
    a) Avoiding all conflict
    b) The ability to speak up without fear of blame or punishment
    c) Eliminating accountability
    d) Allowing only senior members to make decisions
    Answer: b) The ability to speak up without fear of blame or punishment
  22. Which approach best supports team empowerment?
    a) Making all decisions at the executive level
    b) Giving the team clear goals and authority to decide how to deliver
    c) Removing all project constraints
    d) Avoiding performance discussions
    Answer: b) Giving the team clear goals and authority to decide how to deliver
  23. What is the purpose of a RACI chart?
    a) To calculate project cost
    b) To define responsible, accountable, consulted and informed roles
    c) To prioritize risks
    d) To measure quality defects
    Answer: b) To define responsible, accountable, consulted and informed roles
  24. What does emotional intelligence help a project manager do?
    a) Avoid stakeholder communication
    b) Understand emotions, build relationships and manage conflict
    c) Eliminate the need for planning
    d) Replace project governance
    Answer: b) Understand emotions, build relationships and manage conflict
  25. A project manager notices declining morale. What should be done first?
    a) Add more status reports
    b) Identify root causes through team conversations
    c) Replace the team
    d) Cancel the project
    Answer: b) Identify root causes through team conversations
  26. What is the main purpose of scope management?
    a) To define and control what is included and excluded from the project
    b) To hire project team members
    c) To approve all invoices
    d) To close contracts
    Answer: a) To define and control what is included and excluded from the project
  27. What is scope creep?
    a) Approved scope reduction
    b) Uncontrolled expansion of project scope
    c) Schedule compression
    d) Risk transfer
    Answer: b) Uncontrolled expansion of project scope
  28. What is the main output of the Create WBS process?
    a) Scope Baseline
    b) Risk Register
    c) Cost Forecast
    d) Stakeholder Register
    Answer: a) Scope Baseline
  29. Which component is included in the scope baseline?
    a) Project charter, business case and benefits plan
    b) Scope statement, WBS and WBS dictionary
    c) Risk register, issue log and change log
    d) Budget, invoices and contracts
    Answer: b) Scope statement, WBS and WBS dictionary
  30. A customer requests an additional feature after scope approval. What should the project manager do?
    a) Add it immediately
    b) Follow the change control process
    c) Reject it automatically
    d) Ask the team to work overtime
    Answer: b) Follow the change control process
  31. What is the purpose of requirements traceability?
    a) To track requirements from origin through delivery and validation
    b) To assign project risks
    c) To approve vendor payments
    d) To create the team charter
    Answer: a) To track requirements from origin through delivery and validation
  32. In an agile project, where are product requirements commonly prioritized?
    a) Issue log
    b) Product backlog
    c) Procurement register
    d) Cost baseline
    Answer: b) Product backlog
  33. Who is typically responsible for prioritizing the product backlog?
    a) Project sponsor
    b) Product owner
    c) Procurement manager
    d) Quality auditor
    Answer: b) Product owner
  34. What is the best approach when requirements are uncertain and likely to change?
    a) Predictive approach only
    b) Agile or adaptive approach
    c) No planning
    d) Close the project early
    Answer: b) Agile or adaptive approach
  35. What is the purpose of Validate Scope?
    a) To formally accept completed deliverables
    b) To inspect team performance
    c) To estimate project cost
    d) To identify new vendors
    Answer: a) To formally accept completed deliverables
  36. What is the difference between Validate Scope and Control Quality?
    a) Validate Scope checks quality; Control Quality accepts deliverables
    b) Validate Scope obtains acceptance; Control Quality checks correctness
    c) Both are the same
    d) Neither involves deliverables
    Answer: b) Validate Scope obtains acceptance; Control Quality checks correctness
  37. What is the purpose of schedule management?
    a) To define, sequence, estimate and control project timing
    b) To approve the business case
    c) To remove stakeholder conflict
    d) To manage only vendor schedules
    Answer: a) To define, sequence, estimate and control project timing
  38. What is the critical path?
    a) The shortest path in the project network
    b) The sequence of activities that determines the project duration
    c) The path with the lowest cost
    d) The list of optional activities
    Answer: b) The sequence of activities that determines the project duration
  39. What happens if an activity on the critical path is delayed?
    a) The project always finishes early
    b) The project finish date may be delayed
    c) The project cost always decreases
    d) The risk register is closed
    Answer: b) The project finish date may be delayed
  40. What is float or slack?
    a) The amount of time an activity can be delayed without delaying the project or milestone
    b) The total project budget
    c) The number of assigned resources
    d) The project quality tolerance
    Answer: a) The amount of time an activity can be delayed without delaying the project or milestone
  41. What is fast tracking?
    a) Adding resources to reduce schedule duration
    b) Performing activities in parallel that were originally planned in sequence
    c) Reducing project scope without approval
    d) Delaying noncritical work
    Answer: b) Performing activities in parallel that were originally planned in sequence
  42. What is crashing?
    a) Adding resources to shorten the schedule
    b) Performing work without approval
    c) Cancelling project activities
    d) Reducing quality testing
    Answer: a) Adding resources to shorten the schedule
  43. What is a major risk of fast tracking?
    a) Increased rework
    b) Lower communication needs
    c) Reduced dependency risk
    d) Guaranteed cost savings
    Answer: a) Increased rework
  44. What is a major risk of crashing?
    a) Lower cost
    b) Increased cost
    c) Fewer resources
    d) No schedule impact
    Answer: b) Increased cost
  45. In agile, what is a sprint?
    a) A fixed timebox for completing selected work
    b) A vendor contract
    c) A final project audit
    d) A risk category
    Answer: a) A fixed timebox for completing selected work
  46. What is the purpose of a daily standup?
    a) To provide a long management report
    b) To inspect progress, coordinate work and identify impediments
    c) To approve the business case
    d) To close the project
    Answer: b) To inspect progress, coordinate work and identify impediments
  47. What does a burndown chart show?
    a) Remaining work over time
    b) Total project cost only
    c) Stakeholder influence
    d) Vendor performance
    Answer: a) Remaining work over time
  48. What does velocity measure in agile?
    a) The team’s completed work per iteration
    b) The number of project stakeholders
    c) The total project budget
    d) The number of project risks
    Answer: a) The team’s completed work per iteration
  49. What is the main purpose of cost management?
    a) To estimate, budget and control project costs
    b) To define team conflict rules
    c) To develop stakeholder power maps
    d) To approve scope changes automatically
    Answer: a) To estimate, budget and control project costs
  50. What is a cost baseline?
    a) The approved version of the time-phased project budget
    b) The total number of team members
    c) The product backlog
    d) The stakeholder engagement plan
    Answer: a) The approved version of the time-phased project budget
  51. What does Earned Value represent?
    a) The budgeted value of completed work
    b) The actual money spent
    c) The total approved budget
    d) The remaining risk reserve
    Answer: a) The budgeted value of completed work
  52. If CPI is less than 1.0, what does it indicate?
    a) The project is under budget
    b) The project is over budget
    c) The project is ahead of schedule
    d) The project has no cost risk
    Answer: b) The project is over budget
  53. If SPI is less than 1.0, what does it indicate?
    a) The project is ahead of schedule
    b) The project is behind schedule
    c) The project is under budget
    d) The project is complete
    Answer: b) The project is behind schedule
  54. What is management reserve used for?
    a) Known risks with planned responses
    b) Unknown-unknown risks or unforeseen work within project scope
    c) Approved team rewards
    d) Routine operational expenses
    Answer: b) Unknown-unknown risks or unforeseen work within project scope
  55. What is contingency reserve used for?
    a) Identified risks with planned responses
    b) Executive bonuses
    c) Unapproved scope changes
    d) Final project celebration
    Answer: a) Identified risks with planned responses
  56. What is the purpose of quality management?
    a) To ensure the project satisfies stated and implied needs
    b) To increase project scope
    c) To eliminate all changes
    d) To reduce stakeholder communication
    Answer: a) To ensure the project satisfies stated and implied needs
  57. What is prevention in quality management?
    a) Finding defects after delivery
    b) Keeping defects out of the process
    c) Accepting all defects
    d) Reducing requirements
    Answer: b) Keeping defects out of the process
  58. What is inspection in quality management?
    a) Finding defects after work is performed
    b) Preventing all risks
    c) Approving the project charter
    d) Creating the cost baseline
    Answer: a) Finding defects after work is performed
  59. What is the cost of quality?
    a) Only the cost of testing
    b) The total cost of conformance and nonconformance
    c) Only the cost of defects
    d) The project management fee
    Answer: b) The total cost of conformance and nonconformance
  60. A project has repeated defects from the same source. What should the project manager use?
    a) Root cause analysis
    b) Fast tracking
    c) Stakeholder mapping
    d) Contract closure
    Answer: a) Root cause analysis
  61. What is the purpose of resource management?
    a) To identify, acquire, develop and manage resources needed for the project
    b) To approve the business case
    c) To control only financial resources
    d) To eliminate project constraints
    Answer: a) To identify, acquire, develop and manage resources needed for the project
  62. What is resource leveling?
    a) Adjusting start and finish dates based on resource availability
    b) Reducing product quality
    c) Increasing project scope
    d) Removing dependencies
    Answer: a) Adjusting start and finish dates based on resource availability
  63. What is resource smoothing?
    a) Adjusting activities within available float without changing the critical path
    b) Adding unlimited resources
    c) Ignoring resource constraints
    d) Cancelling project activities
    Answer: a) Adjusting activities within available float without changing the critical path
  64. A key expert is unavailable during a critical activity. What should the project manager do?
    a) Update the resource plan and evaluate schedule impact
    b) Ignore the issue
    c) Cancel the project
    d) Remove quality requirements
    Answer: a) Update the resource plan and evaluate schedule impact
  65. What is the best way to improve a virtual team’s collaboration?
    a) Reduce communication
    b) Establish clear communication norms and shared tools
    c) Avoid meetings completely
    d) Assign work without context
    Answer: b) Establish clear communication norms and shared tools
  66. What is the purpose of risk management?
    a) To identify, analyze, respond to and monitor uncertainty
    b) To remove all uncertainty
    c) To increase project cost
    d) To avoid stakeholder engagement
    Answer: a) To identify, analyze, respond to and monitor uncertainty
  67. What is a risk register?
    a) A document containing identified risks, analysis and response information
    b) A list of completed deliverables
    c) A vendor invoice file
    d) A project team directory
    Answer: a) A document containing identified risks, analysis and response information
  68. What is a risk owner?
    a) The person responsible for monitoring and managing a risk response
    b) The person who approves all project costs
    c) The person who creates the charter
    d) The person who closes the project
    Answer: a) The person responsible for monitoring and managing a risk response
  69. What is risk avoidance?
    a) Changing the plan to eliminate the threat
    b) Accepting the risk without action
    c) Sharing the risk with the customer only
    d) Increasing risk probability
    Answer: a) Changing the plan to eliminate the threat
  70. What is risk mitigation?
    a) Reducing the probability or impact of a threat
    b) Ignoring a risk
    c) Increasing scope
    d) Closing the issue log
    Answer: a) Reducing the probability or impact of a threat
  71. What is risk transfer?
    a) Moving ownership or impact of a threat to a third party
    b) Removing all risks
    c) Increasing the project budget without approval
    d) Accepting the risk internally
    Answer: a) Moving ownership or impact of a threat to a third party
  72. What is risk acceptance?
    a) Taking no proactive action except monitoring or preparing contingency
    b) Eliminating the risk completely
    c) Assigning the risk to another project
    d) Hiding the risk from stakeholders
    Answer: a) Taking no proactive action except monitoring or preparing contingency
  73. What is an opportunity in risk management?
    a) A negative uncertain event
    b) A positive uncertain event
    c) A confirmed issue
    d) A project constraint
    Answer: b) A positive uncertain event
  74. What is the best response to a high-probability, high-impact threat?
    a) Ignore it
    b) Develop a clear response plan and assign an owner
    c) Wait until it becomes an issue
    d) Remove it from the risk register
    Answer: b) Develop a clear response plan and assign an owner
  75. What is the difference between a risk and an issue?
    a) A risk is uncertain; an issue has already occurred
    b) A risk has occurred; an issue is uncertain
    c) They are the same
    d) Issues are always positive
    Answer: a) A risk is uncertain; an issue has already occurred
  76. What is the purpose of procurement management?
    a) To obtain products, services or results from outside the project team
    b) To define only internal team roles
    c) To create the product backlog
    d) To approve employee vacations
    Answer: a) To obtain products, services or results from outside the project team
  77. Which contract type gives the buyer the highest cost certainty?
    a) Cost-reimbursable
    b) Time and materials
    c) Fixed-price
    d) Letter of intent
    Answer: c) Fixed-price
  78. Which contract type is most useful when the scope is uncertain and flexibility is needed?
    a) Cost-reimbursable
    b) Firm fixed-price
    c) Fixed-price incentive fee only
    d) Purchase order only
    Answer: a) Cost-reimbursable
  79. What is a major risk of a time and materials contract?
    a) The buyer may have less cost control if work is not capped
    b) The seller receives no payment
    c) The scope can never change
    d) The contract requires no monitoring
    Answer: a) The buyer may have less cost control if work is not capped
  80. What is the purpose of a make-or-buy analysis?
    a) To decide whether work should be performed internally or procured externally
    b) To approve final acceptance
    c) To close the project charter
    d) To assign stakeholder power
    Answer: a) To decide whether work should be performed internally or procured externally
  81. What is integrated change control?
    a) Reviewing, approving and managing changes across the project
    b) Allowing any stakeholder to change scope
    c) Avoiding all change requests
    d) Updating only the project schedule
    Answer: a) Reviewing, approving and managing changes across the project
  82. Who typically approves major change requests in a formal project environment?
    a) Change Control Board
    b) Any team member
    c) Vendor only
    d) End user only
    Answer: a) Change Control Board
  83. What should a project manager do before approving a scope change?
    a) Analyze impact on scope, schedule, cost, quality, risk and value
    b) Start the work immediately
    c) Ignore the sponsor
    d) Remove the change from the log
    Answer: a) Analyze impact on scope, schedule, cost, quality, risk and value
  84. What is the purpose of lessons learned?
    a) To capture knowledge for current and future projects
    b) To assign blame
    c) To replace quality control
    d) To avoid stakeholder communication
    Answer: a) To capture knowledge for current and future projects
  85. When should lessons learned be captured?
    a) Only at the end of the project
    b) Throughout the project and at closure
    c) Only before the charter is approved
    d) Only during procurement
    Answer: b) Throughout the project and at closure
  86. What is the purpose of project closure?
    a) To formally complete the project or phase
    b) To start planning
    c) To add new scope
    d) To remove stakeholder records
    Answer: a) To formally complete the project or phase
  87. Before closing a project, what should the project manager confirm?
    a) All deliverables are accepted and closure activities are complete
    b) All risks were avoided
    c) The project had no changes
    d) No lessons were learned
    Answer: a) All deliverables are accepted and closure activities are complete
  88. In agile, what is the purpose of a retrospective?
    a) To inspect the product increment only
    b) To improve team process and collaboration
    c) To approve the project charter
    d) To cancel the backlog
    Answer: b) To improve team process and collaboration
  89. In agile, what is the purpose of a sprint review?
    a) To demonstrate completed work and gather feedback
    b) To privately evaluate team members
    c) To approve vendor contracts
    d) To create the business case
    Answer: a) To demonstrate completed work and gather feedback
  90. What is the best reason to use a hybrid delivery approach?
    a) The project has both stable and evolving components
    b) The team wants to avoid planning
    c) The sponsor does not want governance
    d) The project has no uncertainty
    Answer: a) The project has both stable and evolving components
  91. A project includes a regulated hardware component and an evolving software component. Which approach is most suitable?
    a) Predictive only
    b) Agile only
    c) Hybrid
    d) No defined approach
    Answer: c) Hybrid
  92. What is tailoring in project management?
    a) Selecting and adapting methods, processes and artifacts to fit the project context
    b) Following every process exactly the same way
    c) Avoiding governance
    d) Eliminating stakeholder input
    Answer: a) Selecting and adapting methods, processes and artifacts to fit the project context
  93. What factor should most influence the choice of project life cycle?
    a) Project uncertainty, requirements stability, risk and delivery needs
    b) The project manager’s personal preference only
    c) The number of meeting rooms
    d) The project title
    Answer: a) Project uncertainty, requirements stability, risk and delivery needs
  94. How can AI best support project management?
    a) By replacing all human judgment
    b) By assisting analysis, forecasting, documentation and decision support
    c) By removing the need for stakeholders
    d) By approving all changes automatically
    Answer: b) By assisting analysis, forecasting, documentation and decision support
  95. What should a project manager do when using AI-generated project recommendations?
    a) Accept them without review
    b) Validate assumptions, data quality and risks before using them
    c) Share confidential data freely
    d) Avoid informing the team
    Answer: b) Validate assumptions, data quality and risks before using them
  96. A project uses AI to estimate schedules. What is a key concern?
    a) AI estimates never need validation
    b) Historical data quality and bias may affect accuracy
    c) AI eliminates all uncertainty
    d) Stakeholders are no longer needed
    Answer: b) Historical data quality and bias may affect accuracy
  97. How should sustainability be considered in project management?
    a) Only after the project closes
    b) As part of planning, decision-making, delivery and benefits evaluation
    c) Only by the finance team
    d) Only if it reduces scope
    Answer: b) As part of planning, decision-making, delivery and benefits evaluation
  98. A project option has a lower upfront cost but creates higher environmental impact and long-term operating cost. What should the project manager recommend?
    a) Select the lowest upfront cost automatically
    b) Evaluate total value, lifecycle impact and stakeholder expectations
    c) Ignore sustainability
    d) Remove the option from discussion without analysis
    Answer: b) Evaluate total value, lifecycle impact and stakeholder expectations
  99. What is the main purpose of benefits realization management?
    a) To ensure project outputs lead to intended business value
    b) To close risks quickly
    c) To increase documentation volume
    d) To avoid measuring outcomes
    Answer: a) To ensure project outputs lead to intended business value
  100. A completed project delivered all outputs, but users are not adopting the solution. What should the project manager focus on?
    a) Claim success because all outputs were delivered
    b) Work with stakeholders to address adoption barriers and realize benefits
    c) Close the project without review
    d) Blame the users
    Answer: b) Work with stakeholders to address adoption barriers and realize benefits